The MRB (manufacturing record book) or MDR (manufacturing data report) is the final dossier of a fabrication project: the bundled evidence that the product was built and inspected in line with the contract, the standards and the approved procedures. The client, the notified body and later the owner of the plant must still be able to work with it years after handover.
In practice the dossier is often thrown together under pressure in the final week, with missing certificates, unsigned reports and tracing work as a result. That is avoidable. This article describes what belongs in an MRB or MDR, in what order, and how to build the dossier digitally during the project so that handover becomes a formality.

The terms are used interchangeably and mean essentially the same: the coherent package of records from a fabrication project. MRB is common in oil, gas and process industry, MDR stems from the ASME world, where the data report forms are part of the package. Other names include handover dossier, fabrication dossier or documentation package.
What goes in is set by the contract together with the application standard. For pressure equipment under PED 2014/68/EU the directive prescribes which technical documentation the manufacturer must be able to produce. For steel structures under EN 1090-2 the quality records underpin the declaration of performance. The table of contents should therefore always be project specific and agreed with the client before fabrication starts.
Depending on scope, a complete dossier contains at least these blocks:
Build the dossier in the order a reviewer thinks, not in the order documents happened to arrive. Common and logical: first the general part with the declaration of conformity and the non conformity register, then design, then material, then fabrication and welding, then inspection and testing, and finally coating and appendices.
Give each section a tab or digital folder with fixed numbering and let the table of contents reference document numbers, not page numbers. The crucial part is the golden thread: from any component it must be possible to follow the chain from drawing to material certificate, to weld, to welder, to WPS, to inspection report. That chain stands or falls with a well kept weld map and weld log.
The biggest improvement for most manufacturers is the moment of compilation. Whoever assembles the dossier after the last weld discovers only then that a certificate is missing, a report is unsigned or a welder worked outside his qualification range. At that point repair is expensive and delays handover.
The solution is simple: set up the digital dossier structure at project start, linked to the table of contents and to the lines of the ITP. Every document is filed in the right place on the day it is created, with a document register tracking the status of each expected item: expected, received, approved. A weekly glance then shows exactly what is missing, while correction is still cheap. Record these arrangements in the ITP and the quality plan.
Dossier reviews keep turning up the same shortcomings:
Have the dossier checked before submission by someone other than the compiler, preferably someone used to reviewing dossiers the way a client or notified body does.
Formally the manufacturer is responsible; in practice compilation is a discipline of its own that demands rigour and knowledge of the standards. On larger projects a dedicated document controller or QA and QC officer pays off, keeping the register, checking documents on receipt and chasing subcontractor dossiers.
If that capacity is not available in house, an independent party can manage the dossier from set up at the start to the final check before submission. DEHAAS provides this as part of its QA and QC support, hands on, across Europe and North America. The dossier then becomes a by product of good project control rather than a final sprint.
A tailored quote in a few clicks. You get an answer from a welding coordinator.
Independently assessed, demonstrably recorded
The questions we are asked most often.
Little in substance: both are the bundled evidence dossier of a fabrication project. MRB is the usual term in oil, gas and process industry, MDR is often used in the ASME context where the data report forms are part of the package. The contract sets the name and the table of contents.
That follows from contract and legislation. For pressure equipment under the PED the manufacturer must keep the technical documentation available for ten years after placing on the market. Process industry clients often require the full service life of the plant. Fix the term in the contract.
Digital is now the norm and the better choice: searchable, copyable and easy to maintain during the project. Some clients and notified bodies additionally require a signed hard copy or wet signatures on specific documents. Agree the format at project start.
The certificate type follows from the standard and the contract; for pressure retaining and structural parts usually a 3.1 certificate to EN 10204. Just as important as the certificate is traceability: a list linking each certificate via heat number to the components in the product.
Just ask it. You get a personal answer from a welding coordinator who has done the work, not from a salesperson.