Anyone placing load-bearing steel or aluminium structures on the EU market needs certified factory production control. FPC is the system that shows your structural components consistently meet their declared performance. It underpins the declaration of performance and CE marking under EN 1090-1.
Many fabricators treat FPC as paperwork dusted off once a year for the audit. That is a missed opportunity. A well-designed FPC prevents errors in the workshop, limits disputes at handover and makes the notified body's audit considerably easier. This article explains what belongs in it and how to set it up in practice.

EN 1090-1 is the harmonised product standard for steel and aluminium structural components under the Construction Products Regulation (EU) 305/2011. Structural components fall under assessment system 2+. The manufacturer is responsible for production and the declaration of performance, while a notified body assesses, certifies and monitors the FPC.
FPC covers all procedures, instructions and records through which the manufacturer controls production. The certificate states, among other things, the highest execution class for which the company has been assessed. Work in a higher class cannot be CE marked under that certificate. Our article on CE marking of steel structures explains how the marking itself works.
EN 1090-1 sets out the elements an FPC must address as a minimum. In practice these are:
Start with how your company actually works, not with a manual. A workable approach:
Keep the system as lean as possible. A procedure that is not followed in the workshop is more likely to produce an audit finding than to help.
The notified body is designated by a Member State and listed in the European NANDO database. Under system 2+ it has two tasks:
The notified body does not approve individual products and does not apply CE marking. That responsibility stays with the manufacturer, who draws up and signs the declaration of performance.
Welding is a special process: its quality cannot be fully verified afterwards. EN 1090-2 therefore refers to ISO 3834 for welding quality requirements, with the part depending on the execution class:
The notified body assesses these requirements as part of the FPC audit. A separate ISO 3834 certificate is not required for EN 1090, but can be worthwhile if you also supply pressure equipment, machinery or other welded products outside construction. Our article on the parts of ISO 3834 explains the differences.
ISO 9001 is not mandatory for EN 1090-1, but the standard does state that a quality management system to ISO 9001, made specific to the requirements of EN 1090-1, satisfies the FPC requirements. If you already hold ISO 9001, build the FPC into it, using the same document control, internal audits and non-conformity handling, supplemented by the product-specific requirements of EN 1090-1 and EN 1090-2.
Conversely, FPC need not be a full ISO 9001 system. For a smaller workshop, a compact FPC focused on materials, welding, dimensions and records is often the most workable. To get the set-up right from the start, consider targeted EN 1090 support.
A tailored quote in a few clicks. You get an answer from a welding coordinator.
Independently assessed, demonstrably recorded
The questions we are asked most often.
That depends on what is already in place. A company with qualified welders, WPSs and working records can be ready for initial inspection within a few months. If welding procedures still need qualifying, that usually sets the timeline.
If you place load-bearing components on the market yourself, yes, even when fabricating to the client's drawings. If you supply welding work or semi-finished parts to a manufacturer who places the end product on the market under its own FPC, that manufacturer can control you as a subcontractor within its system.
The notified body records findings and sets a deadline for resolving them. Minor findings usually need an action plan with evidence of correction. Serious ones can lead to suspension or withdrawal of the certificate.
Yes, through an extension audit by the notified body. You must demonstrate that the system, welding coordination, qualifications and testing meet the EXC3 requirements, including ISO 3834-2.
Just ask it. You get a personal answer from a welding coordinator who has done the work, not from a salesperson.