Not every welded joint calls for a qualified welding procedure. Yet fabricators are asked for WPQRs more and more often, by certification bodies, main contractors and end clients. The obligation rarely comes from a single source: it follows from product standards such as EN 1090-2, from quality systems such as ISO 3834, from legislation such as PED 2014/68/EU, or simply from the contract.
This article sets out when a WPQR is mandatory, when a lighter alternative will do and when you need no qualification at all. That prevents you from qualifying unnecessarily, or worse, discovering during an audit or handover that the evidence is missing. For the basics, see our article on the difference between a WPS and a WPQR.

For load-bearing steel structures under EN 1090-2, the qualification requirement depends on the execution class, EXC1 to EXC4. The class follows from the consequence of failure and the type of loading, and is specified by the designer or client.
ISO 3834 defines quality requirements for fusion welding at three levels. Under ISO 3834-2 (comprehensive) and ISO 3834-3 (standard), the manufacturer must demonstrate that the welding procedures in use are qualified to the applicable standards. Only ISO 3834-4, the elementary level, has no such requirement.
If you are certified, or wish to be, to ISO 3834-2 or -3, a coherent set of WPQRs and associated WPSs is part of the system. The certification body checks not only that the documents exist, but also that their ranges of qualification cover your actual production. That is where things often go wrong in practice: the file matches the work of five years ago, not the current order book.
Pressure equipment under PED 2014/68/EU must meet the essential safety requirements of Annex I. For equipment in category II and above, the procedures for permanent joining, including welding, must be approved by a competent third party: a notified body or a recognised third-party organisation. An in-house qualification without that approval is not sufficient.
In practice this means the procedure test is witnessed and assessed by such a body, usually against EN ISO 15614-1 as the harmonised standard. Welders and operators must likewise be third-party qualified for category II and above. If you build pressure vessels, piping or installations within the scope of the PED, assume the WPQR requirement applies almost without exception.
Even without a legal or normative obligation, a WPQR may simply be required by contract. Major clients in oil and gas, offshore, infrastructure and machine building routinely state in their purchase specifications that welding procedures must be qualified, often with requirements on top of the standard: additional impact tests, lower test temperatures, corrosion testing or restrictions on the range of qualification.
Always read the specification in full before you price the work. An existing WPQR that is valid under the standard can be rendered unusable by a single clause in the client specification. Conversely, some clients accept qualifications under other systems, such as ASME IX, provided equivalence is demonstrated. Clarify this before the order rather than after.
There are genuine cases where qualification is not mandatory:
Note that no obligation does not mean qualification is pointless. A WPQR proves process control even where none is required, and can be a commercial advantage in tenders.
To determine whether you need a WPQR, work through these questions:
If you are unsure, DEHAAS will review your requirements and existing qualifications independently, and where needed guide a new WPQR qualification from pWPS to approved record.
A tailored quote in a few clicks. You get an answer from a welding coordinator.
Independently assessed, demonstrably recorded
The questions we are asked most often.
Yes, from EXC2 onwards EN 1090-2 requires qualified welding procedures. At EXC2 some alternative routes remain open besides the procedure test to EN ISO 15614-1, such as a standard welding procedure to EN ISO 15612, within the limits of the standard.
For category I, yes. From category II upwards the qualifications must be approved by a notified body or a recognised third-party organisation. In-house qualification alone is not sufficient.
Not automatically. Client specifications may demand additional tests or restrictions that make a standard-compliant WPQR unusable for that project. Always check the range and the supplementary requirements against the project specification.
In principle yes, as the process is an essential variable. You can, however, combine several processes in one test piece, so a single test covers multiple processes within the rules of EN ISO 15614-1.
Just ask it. You get a personal answer from a welding coordinator who has done the work, not from a salesperson.