The factory acceptance test (FAT) and the final inspection are the last opportunities to assess a product at the manufacturer before it leaves the workshop. Anything missed here will surface later on site or at the end client, at a far higher cost. A well prepared FAT and final inspection often make the difference between a smooth handover and weeks of repairs, argument and delay.
The terms are often used interchangeably. The final inspection is the end check of the product itself: dimensions, welds, finish, coating, marking and documentation. The FAT goes a step further and demonstrates that an installation, skid or machine performs as specified, for example through a pressure test, a functional test or a trial run. This article covers both: preparation, the checklist, the role of an independent inspector and where things commonly go wrong.

For a static product such as a steel structure, a pipe spool or a tank without moving parts, a final inspection is usually sufficient. For assembled equipment with pumps, valves, instrumentation or controls, the client will want to see the whole system working before shipment. A FAT then consists of a final inspection plus functional tests to a previously approved test procedure.
Which of the two applies, and who must attend, belongs in the contract and the inspection and test plan. If the FAT is a hold point, nothing may be packed or shipped without release. Our article on how to write an ITP explains how to set those points.
Most problems during a FAT come down to poor preparation. Well before the test date, arrange at least the following:
An internal pre FAT by the manufacturer a few days before the formal test is strongly recommended. Whatever fails there can still be fixed without an audience.
A final inspection follows a fixed checklist derived from the drawing, specification and ITP:
Every party at a FAT has its own interest. The manufacturer wants release and payment, the client wants certainty and the project team wants to keep the schedule. An independent inspector assesses against the agreed criteria, free of those interests. They witness the tests, check the test set up, assess the results and record deviations factually.
A good inspector does more than tick boxes. They notice a hold time that is too short, a pressure gauge used outside its useful range, or a welder on the report who was not qualified to ISO 9606-1 for that position and material. See our fabrication inspection service for how DEHAAS fills this role.
More and more projects use digital release. The inspector records findings with photos, measured values and locations, and the report is available to all parties the same day. The inspection release note is signed digitally and linked straight to the dossier.
The benefit is not only speed. Digital release forces clarity: every item has a status and every deviation an owner and a deadline. Open items move to a punch list, and whatever was released can be demonstrated afterwards. Agree the format in advance, and who may sign for which party.
The same mistakes keep recurring:
A complete dossier on FAT day is achievable if it is built during fabrication rather than afterwards. Our article on MRB and MDR structure explains how.
A tailored quote in a few clicks. You get an answer from a welding coordinator.
Independently assessed, demonstrably recorded
The questions we are asked most often.
A FAT takes place at the manufacturer before shipment. A SAT, or site acceptance test, follows installation at the final location and demonstrates that the system works in its real environment. A successful FAT reduces the risk of surprises at the SAT but does not replace it.
The deviations are recorded in an NCR or on a punch list and the manufacturer corrects them. Depending on severity, a full retest or a reassessment of the affected items follows. Agree beforehand who pays for a retest and an additional inspection visit.
Only with the explicit agreement of the client. Minor items that do not affect function or safety are sometimes closed out on site after delivery. Record them with an owner and a deadline and make them a condition of the release.
It depends on size and complexity. A single structural item can be assessed in a few hours; a skid with piping, instrumentation and functional tests easily takes one or more days, including document review.
Just ask it. You get a personal answer from a welding coordinator who has done the work, not from a salesperson.
Send your request Call 06 29 72 37 91